PV Wastewater Reduction and Reuse Project in China
QT:Nov 18, 2026

Industrial Wastewater Reduction & Reuse

This project treats the production wastewater of a photovoltaic (PV) manufacturer in Zhangjiagang, Jiangsu, China, for discharge reduction and water reuse. Built in two phases, it combines ultrafiltration, softening resin and reverse osmosis, with a total reuse volume of 1,460 m³/day and a discharge of only 40 m³/day.

1,460
m³/day
Total Reuse Volume
40
m³/day
Discharge
2 Phases
Commissioned in
2014 and 2017

enhance-this-image-1

Phase I Project Site

enhance-this-image-2

Phase II Project Site

PROJECT OVERVIEW

Project Information

Project NamePV Wastewater Reduction and Reuse Project (Phase 1 & 2)
CapacityPhase 1: 1,500 m³/day · Phase 2: 400 m³/day
LocationZhangjiagang, Jiangsu Province, China
Commissioning DatePhase 1: 2014 · Phase 2: 2017
Key TechnologyUltrafiltration, softening resin, reverse osmosis

PV Wastewater Reclamation Process Flow

Phase 1: Pretreatment + Low-Pressure Concentration → Phase 2: Softening + High-Pressure Concentration | Permeate Reuse · Compliant Discharge

process_flow_bold_EN (1)

Phase 1 | Pretreatment + Low-Pressure Concentration
Pretreatment handles equalization, coagulation and settling to remove suspended solids and part of the organics. Ultrafiltration retains colloids and macromolecules to protect the membrane feed. Low-pressure RO performs the initial concentration, and its permeate goes straight to the reuse system.
Phase 2 | Silica/Fluoride Removal + High-Pressure Concentration
The Phase 1 concentrate first passes through silica and fluoride removal, then softening resin removes hardness ions to control scaling risk. High-pressure RO achieves high-ratio concentration and volume reduction, recovering more permeate.
Permeate Reuse & Final Discharge
RO permeate from both phases flows into the fresh water reuse system and is reused in production. The high-pressure RO concentrate is treated and discharged in compliance with standards, achieving wastewater reduction and resource recovery.

OPERATING DATA

Performance Targets Achieved

IndicatorPhase 1Phase 2
Recovery Rate (R)75%90%
Operating Pressure (P)15 bar45 bar
Reuse & DischargeTotal reuse 1,460 m³/day, discharge 40 m³/day